Engineer's Toolkit Engineer's Toolkit — IS codes · 52+ formulas · 13 calculators · Glossary — offline on Android
Download on Android
IS 3370: 2009

Code of Practice for Concrete Structures
for Storage of Liquids

The primary standard for the design and construction of liquid-retaining concrete structures — overhead tanks, ground-level reservoirs, underground sumps, and water treatment structures. The 2009 revision replaced the 1965 edition and introduced limit state design with explicit crack width control.

2009
Replaces: IS 3370 : 1965
Committee: CED 2
Pages: 60 (combined)

📋 2009 Revision: IS 3370:2009 is a significant revision from the 1965 edition. It adopts limit state design (per IS 456), introduces explicit crack width limits, and updates material requirements. The four-part structure is retained: Part 1 (general), Part 2 (RCC), Part 3 (prestressed), Part 4 (design tables).

Scope & Parts Overview Cl. 1.1

IS 3370 applies to concrete structures used for the storage of liquids — primarily water, but also other liquids with similar properties. It covers structures at all levels: overhead, ground-level, and underground.

PartTitleCoverage
Part 1General RequirementsMaterials, workmanship, inspection, testing
Part 2Reinforced Concrete StructuresRCC design — walls, floors, roofs, joints
Part 3Prestressed Concrete StructuresPrestressed tanks; no tension in concrete
Part 4Design TablesMoment and shear coefficients for standard tank geometries
Structure TypeExamplesKey Design Concern
Overhead TankElevated RCC tank on stagingSeismic forces on staging; sloshing
Ground-Level TankService reservoir, sumpHoop tension in walls; base pressure
Underground TankUnderground sump, cisternUplift when empty; earth pressure
ReservoirLarge open storage basinLong wall spans; temperature effects
Materials & Mix Requirements Cl. 4, Part 1

Liquid-retaining structures demand denser, less permeable concrete than ordinary RCC. IS 3370:2009 specifies stricter material requirements to ensure water-tightness throughout the structure's service life.

ParameterRequirementRemarks
Minimum concrete gradeM30For all water-retaining surfaces; M25 not permitted
Minimum cement content320 kg/m³Ensures adequate paste for impermeability
Maximum w/c ratio0.45Lower w/c = lower permeability
Preferred cement typePPC or PSCPortland Pozzolana / Slag cement — reduced permeability, lower heat
AdmixturesIntegral waterproofing compounds permittedMust not affect concrete strength or durability
AggregateWell-graded; max size 20 mm for walls < 200 mm thickEnsures proper compaction around reinforcement
⚠️

M30 is the Absolute Minimum Unlike IS 456 where M20 is the minimum for RCC, IS 3370 mandates M30 as the minimum grade for all water-retaining structures. Using M25 — even with waterproofing admixtures — does not comply with IS 3370:2009.

PPC / PSC Preferred Portland Pozzolana Cement (PPC) and Portland Slag Cement (PSC) are preferred over OPC for liquid-retaining structures. The pozzolanic reaction fills capillary pores, significantly reducing permeability and improving long-term durability.

Crack Width Control Cl. 7, Part 2

Crack width control is the most critical design check in IS 3370. Even hairline cracks allow water seepage and lead to reinforcement corrosion. The 2009 revision introduced explicit crack width limits and calculation methods.

Surface / ExposureLimiting Crack WidthRemarks
Water-retaining face (normal)0.2 mmFace in contact with stored liquid
Severe exposure / aggressive liquid0.1 mmSewage, chemicals, coastal environment
Non-water-retaining face0.3 mmPer IS 456 general limit
w = 3 acr × εm / [1 + 2(acr − cmin) / (h − x)]
Crack width formula — IS 456 Annex F (adopted by IS 3370) — acr = distance from point to nearest bar, εm = mean strain
Direct tensionHoop tension in cylindrical walls; entire section in tension — critical for crack control
Bending tensionTension on one face due to bending; neutral axis exists — less critical than direct tension
CombinedBending + direct tension (e.g., rectangular tank walls) — both components must be checked
ℹ️

Crack Width Governs Steel Area In most liquid-retaining structures, the required steel area is governed by the crack width limit — not by the ultimate limit state (strength). This typically results in more steel than a pure strength design would require.

Cover Requirements Cl. 6.1, Part 2

Cover requirements for liquid-retaining structures are more stringent than IS 456 general requirements, reflecting the aggressive environment and the need to protect reinforcement from moisture ingress.

Surface / LocationMinimum Nominal CoverRemarks
Water-retaining face45 mmFace in direct contact with stored liquid
Non-water-retaining face35 mmOuter face of tank walls, roof soffit
Underground structures50 mmWalls and base slab in contact with soil/groundwater
Prestressed concrete50 mm (water face)Additional protection for prestressing tendons
⚠️

Cover Tolerance IS 3370 requires that cover be maintained within ±5 mm of the nominal value. Use of proper cover blocks (chairs) is mandatory — tying bars to formwork or using inadequate spacers is not acceptable for water-retaining structures.

Design Approach Cl. 5, Part 2

IS 3370:2009 adopts the Limit State Design framework of IS 456, with an additional serviceability check for crack width. The design must satisfy both the ultimate limit state (strength) and the serviceability limit state (crack width).

Design CheckMethodLoad Factor
Ultimate Limit State (strength)Per IS 456 — factored loads1.5 (DL + LL)
Serviceability — Crack WidthIS 456 Annex F formula1.0 (service loads)
Prestressed tanks — no tensionFull prestress maintained under all loads
Direct tension designHoop tension = γ × w × r (cylindrical walls)1.5 (factored)
T = γf × w × H × r / 2
Hoop tension in cylindrical tank wall — w = unit weight of liquid, H = depth, r = radius
Ast = T / (0.87 × fy)
Steel area for hoop tension (ULS) — then check crack width at service load
ℹ️

Two-Stage Design Process Step 1: Design for strength using factored loads per IS 456. Step 2: Check crack width at service loads using IS 456 Annex F. If crack width exceeds the limit, increase steel area (not section size) until the crack width criterion is satisfied.

Joints in Liquid-Retaining Structures Cl. 8, Part 2

Joints are the most vulnerable locations for leakage. IS 3370 classifies joints by their function and specifies appropriate water stops and sealants for each type.

Joint TypePurposeWater Stop RequiredSpacing
Construction JointBetween successive concrete poursYes — PVC or rubber water stopAs required by pour sequence
Expansion JointAccommodate thermal expansion/contractionYes — with flexible sealant20 – 30 m spacing
Contraction JointControl cracking due to shrinkageWater stop + sealant10 – 15 m spacing
Movement JointAllow differential settlementFull water stop assemblyAt structural discontinuities
PVC Water StopDumbbell-shaped PVC strip cast into concrete at joint; most common type for construction joints
Rubber Water StopNatural or synthetic rubber; more flexible than PVC; used at movement joints
Hydrophilic StripSwells on contact with water to seal the joint; used as secondary seal at construction joints
⚠️

Water Stop Continuity is Critical Water stops must be continuous around the full perimeter of the joint — including corners. Any break, splice failure, or displacement during concreting creates a direct leakage path. Inspect water stop position before every pour.

Roof Slab Design Cl. 9, Part 2

The roof slab of a liquid-retaining structure must be designed for structural loads and also provide a waterproof cover to prevent contamination of stored water and protect the structure from weathering.

ParameterRequirementRemarks
Minimum slab thickness150 mmEnsures adequate cover and waterproofing layer
Design methodSimply supported or continuous per IS 456Continuity reduces mid-span moments
Waterproofing layerRequired on top surfaceBrick bat coba, IPS, or membrane waterproofing
Inspection manholeMinimum one per compartmentFor cleaning and inspection access
VentilationRequired for enclosed tanksPrevents vacuum/pressure build-up during filling/emptying
Slope of roofMinimum 1:50 for drainagePrevents ponding on roof surface

Roof Live Load IS 3370 requires the roof slab to be designed for a minimum live load of 1.5 kN/m² for inaccessible roofs and 3.0 kN/m² for accessible roofs (per IS 875 Part 2). The weight of the waterproofing layer must also be included as dead load.

Water Tightness Testing Cl. 10, Part 1

Every liquid-retaining structure must be tested for water tightness before being put into service. IS 3370 specifies a standardised water tightness test procedure with clear acceptance criteria.

Test StepProcedure
1. PreparationAllow concrete to cure for minimum 28 days; clean interior surfaces
2. FillingFill tank with clean water to the design full supply level
3. Absorption periodAllow 7 days for initial absorption into concrete pores (do not measure during this period)
4. MeasurementRecord water level at start and end of 24-hour observation period
5. AcceptanceCheck drop against acceptance criteria below
Acceptance CriterionLimitBasis
Maximum water level drop in 24 hours10 mmAbsolute limit
Maximum loss as fraction of tank capacity1/500 of tank capacity per dayProportional limit for large tanks
Governing criterionWhichever is less (more stringent) governs
ℹ️

Evaporation Correction During the 24-hour test period, evaporation losses must be measured using an open evaporation pan placed near the tank. The measured evaporation is subtracted from the total water level drop to obtain the actual leakage loss.

⚠️

Failed Test Remediation If the tank fails the water tightness test, the source of leakage must be identified and repaired using approved crystalline waterproofing compounds or epoxy injection. The test must be repeated after repairs and the 7-day absorption period.

← Back to IS Codes Directory